Nursery school
The reconstruction of the nursery school
The nursery school operates in a 150-year-old mansion. For lack of insulation
the walls are always humid due to soil humidity the expert's study states.
Owing to the plaster the water cannot leave outside only inside the building.
As a consequence all the walls are humid causing unhealthy, stuffy air.
The floor was made of wood, it is in critical condition as well as the
roof. There is an urgent need for functional and structural reconstruction.
The condition survey was carried out in November 2002.
The local council has built the reconstruction in the economy program for
the period of 2000-2006.
The local council's main aim to ensure all the necessary requirements for
school maintaining as well as to introduce integrated education for Roma
children and pupils with special education needs. Building reconstruction
(all floors), building enlargement, modern classroom equipments are needed
to reach the targets. The building-maintainer, the local government of
Pusztamagyaród participates directly from the assistance.
The local government's main aim to ensure all the necessary requirements
for the maintaining, as well as to introduce integrated education.
Main goals:
-reconstruction of the 324,25 square metres building
-175,61 square metres enlargement for kitchen and office
-building of a 72 square metres roofed terrace
- purchasing modern equipment, tools, toys to the classrooms and the
playing- ground
The project covers the whole building.
With the project implementation the candidate would contibute to provide
equal opportunities in the region of Letenye.
Integrated education for children with special needs are involved in
the deed of foundation of the nursery and primary school, as well. The
local government also supports integrated education for Roma children
and claims state norms from the year of 2005.
Introduction of the target group
Most of the concerned children, especially Roma children, in the project
come from socially disadvantaged settlements. 23 children (55%) in the
nursery school participate permanent child care assisstance.
The present number of the children (around 40) appears permanent for the
future; the rate of Roma and socially disadvantaged children is growing.
The requirements of the target group are determined by the social composition.
The conditions and qualifications of the Roma population is similar to
the other socially disadvantaged regions. More than 50% of the students
participate permanent child care assisstance. In the nursery school this
rate is 35%. In the next years the rate of the Romas is growing. Due to
the children's social circumstances, the unskilled parents these children
should get pre- school education from the age of three to prepare them
for the primary school. Owing to the nursery school is in a critical condition
without reconstruction we should close it. Children should commute to the
neighbour settlements, which is unsolvable.
30. September 2005
Declaration of assisstance contract in the office of VÁTI in Szombathely.
30. September 2005- 22. May 2006
Public procurements were carried out concerning project-management, technological
requirements. The auditor and legal expert were charged. The whole management
was ready to carry out the project.
Due to the size of the project open public procurement process was announced.
He tender plan was carried out according to the documentations. The tender
was published on 20 February 2006 in the Közbeszerzési Értesítő (volume
22, Ref. No.4440/2006). On 10 April the contractor was charged. The building
plan was completed.
5 May 2006
MÍVES Építőipari Kft. signed the building contract then received the building
site.
Make in the contract
Nursery School
Before Renovation
During Building
2006. 05. 26
2006. 06. 15
2006. 07. 06
2006. 07. 24
2006. 08. 28
2006. 09. 01
2006. 09. 18
2006. 10. 06
2006. 10. 11
2006. 10. 18
2006. 10. 25
2006. 11. 08
2006. 11. 16
2006. 11. 19
|
|